BE-Mine site indoor diving center
Beringen, Belgium, Europe
Sector Sports
Client Be-MINE nv, Koolmijnlaan 201, 3582 Beringen, BE
Architect Eiland 7 Architecten, Elzendreef 45, 3110 Rotselaar, BE
Intervention Construction and Renovation
Scope Study and following up MEP
GFA 3,000 m2
Project status completed
Study June 2014 - April 2015
Execution June 2015 - December 2016
Total technical installations cost: | 1.837.202,44 € excl. vat |
Total construction cost: | 9.000.000,00 € excl. vat |
Project description:
The largest indoor diving centre in Europe consists of a heated pool with a diameter of 36 metres, a depth of 10 metres and a volume of 6.2 million litres of water.
In this diving centre, various underwater sports such as diving, freediving and snorkelling among 5.000 tropical freshwater fish are offered year-round. In addition, events, initiations and training courses are organised. In the brasserie, one can enjoy gastronomic dining.