Home / Projects / Industry / BARCO LOGISTIC CENTER

BARCO LOGISTIC CENTER

Kuurne, Belgium, Europe

Sector Industry
Client Futurn nv, Nijverheidskaai 3 boîte 3/32, 8500 Kortrijk, BE
Architect Snoeck & Partners Architectuur & Engineering nv, Engelse Wandeling 70, 8510 Kortrijk-Marke, BE
Intervention Construction
Scope Study and following up MEP
GFA 4,446 m2
Project status completed
Study August 2013 - February 2014
Execution September 2014 - October 2014

Sustainable Features

water management
water management
heat recovery
heat recovery

Total technical installation cost: 341.779,27 € VAT excluded

Total construction cost: 2.162.980,00 € VAT excluded

K-level: 24

 

This is the first phase of the reconversion of the site. The new construction holds a warehouse for the storage of production materials and finished products.

The techniques applied are elementary for this building type, based on air heaters and destratification fans. The building is fitted in the existing sprinkler installation. The lighting is a modular rail system, that is flexible to adapt to any new function that may be assigned to this section.

The phasing within this project was taken into account, whereby the building is now integrated in the existing installations. In the next phase of the reconversion, the building will be powered autonomously.

More information on Barco.